The Project

  • $2Bn+ Research Campus
  • Greenfield site
  • Linac, Tunnels, Instrumentation Halls, Offices, Utilities
 

How was Flow used?

  • Structured the programme of design works
  • Supported the team to define the complexity of their process
  • Optimized delivery sequence of design for construction packages
  • Integrated design & procurement schedules
  • Supported the design of the emerging organisation
  • Active management of the delivery of design
 

Benefits

  • Design-construction optimisation led to achievement of target cost agreement and subsequent contract award
  • Established, implemented and managed sponsor board governance, leadership and reporting to pan-European stakeholder groups in addition to programme governance and reporting
  • Significant savings in soft costs
  • Schedule optimisation provided assurance of the baseline schedule.